Colovore files $430M Fort Worth data center permit a day after Texas pause

The Denton County application sets a Dec. 1 start and a Dec. 1, 2028 completion while a city moratorium and the governor's permit pause are still in motion.

Colovore has filed for a permit to build a $430 million data center in the Denton County portion of Fort Worth, a filing that landed one day after Governor Greg Abbott ordered a pause on issuing data center permits, according to Connect CRE.

The application describes a one-story building with four data halls and 156,500 square feet of data center space, along with a 42,000-square-foot screened equipment yard and an administrative area, with an estimated start on Dec. 1 and completion on Dec. 1, 2028.

More than a month before the filing, the Fort Worth City Council began the process of implementing a 90-day moratorium on accepting, processing and approving new data center applications, according to Community Impact via Connect CRE; the governor's pause arrived the day before the application. How far the application gets is not something the coverage resolves.

A Texas budget filed into a closing window

Denton County would slot into a Texas footprint that already includes an Austin data center, sites under construction in Fort Worth and Mesquite, and a planned project in Johnson County, but the cost figure is worth reading against the developer's last Texas budget: the Hutto project this publication has covered broke ground in September at $280 million, down from a $500 million original price for nearly the same building. Whether Denton County reprices the same way is unknown, but the filing shows a sponsor willing to put a nine-figure number into a queue that two layers of government have just made longer.

The application reads like a developer underwriting the permitting calendar as the scarce asset, the place where data center capital now prices risk, ahead of the land itself.

The completion date is the tell. Dec. 1, 2028 lands in the year the build-over-buy trade has been aiming at, and the bet now carries a policy rider in the form of a pause order issued the day before the paperwork. The dates to watch are the council's 90-day process and Colovore's Dec. 1 start; the second is only reachable if the first clears.

Colovore's Texas budgets: Hutto repriced, Denton County filed
Hutto's budget fell $220M between original price and groundbreaking
Hutto — Hutto — Denton C
PRED ARCHIVE (HUTTO, SEPT 2026), PERMIT FILING VIA CONNECT CRE
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
More from Private Real Estate Daily
Sectors

infinitSpace picks downtown Los Angeles for first U.S. flex location

The Europe-based operator will manage roughly 32,000 square feet at 612 S. Broadway for an owner that keeps the building, and is targeting 30 new U.S. locations over the next 24 months.
Sectors

Marcus & Millichap: D.C. retail transaction activity up 30% as Northern Virginia vacancy holds

More retail space was leased than vacated across the metro in 2025, while District and Maryland suburban vacancy rose, according to the brokerage's report.
Capital

Edens closes $850 million for retail; Declaration registers third real estate fund

One is a completed commitment for retail acquisitions and development; the other is a registration with no strategy disclosed and no dollars sold.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Real Estate Daily, in your inbox every weekday. Free.